Question: 19 activity A B D E F G EY Immediate predecesory Nonc A A B D EF Oplanista Time (web) 2 4 2 4 8

19 activity A B D E F G EY Immediate predecesory Nonc A A B D EF Oplanista Time (web) 2 4 2 4 8 2 2 Most likely Pesc Time (wecks) Time ( wk) 4 6 6 8 3 4 7 10 10 5 8 2 2 Give the information in the table, what is the probability the the project could be completed in 28 weeks? (2 Points)