Question: 190 Chapter 6 evvelles a Project Plus Case Greendale Stadium Case The G&E Company is preparing a bid to build the new 47.000 seat Greendale

190 Chapter 6 evvelles a Project Plus Case

190 Chapter 6 evvelles a Project Plus Case

190 Chapter 6 evvelles a Project Plus Case Greendale Stadium Case The G&E Company is preparing a bid to build the new 47.000 seat Greendale baseball stadium. The construction must start July 1, 2011, and he completed in time for the start of the 2014 season. A penalty clause of $100,000 per day of de- lay beyond May 20, 2014, is written into the contract. Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $2 million on the project. He also said if they are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball parks with modern luxury boxes ASSIGNMENT Given the information provided in Table 6.3, construct a network schedule for the stadium project and answer the following questions: 1. Will the project be able to be completed by the May 20 deadline? How long will it take? 2. What is the critical path for the project? 3. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule. ID TABLE 6.3 Greendale Stadium Case Duration Predecessors! 1 2 3 4 5 6 7 8 9 = 5 Activity Baseball Stadium Clear stadium site Demolish building Set up construction site Drive support piling Pour lower concrete bowl Pour main concourse Install playing field Construct upper steel bowl Install seats Build luxury boxes Install jumbotron Stadium infrastructure Construct steel canopy Light installation Build roof supports Construct root Install roof tracks Install roof Inspection 11 12 13 14 15 16 17 18 19 20 70 days 30 days 70 days 120 days 120 days 120 days 90 days 120 days 140 days 90 days 30 days 120 days 75 days 30 days 90 days 180 days 90 days 90 days 20 days 2 3 2 5 3,6 3.6 3,5 7,9 79 7,9 7,9 10 14 6 16 16 17,18 8,11,13,15,19 Chapter 6 Developing a Project Plan 199 CASE APPENDIX: TECHNICAL DETAILS OF THE GREENDALE BASEBALL STADIUM The baseball stadium is an outdoor structure with a retractable roof. The project begins with clearing the site, an activity that lasts 70 days. Once the site is clear. work can start simultaneously on the structure itself and demolishing an adjacent building site. This demolition is necessary to create a construction stage for stor- ing materials and equipment. It will take 30 days to demolish the buildings and another 70 days to set up the construction site. The work on the stadium begins by driving 160 support pilings, which will take 120 days. Next comes the pouring of the lower concrete bowl (120 days). Once this is done and the construction site has been set up, then the pouring of the main concourse (120 days), the installation of the playing field (90 days), and the con- struction of the upper steel bowl can occur (120 days). Once the concourse and upper bowl are completed, work can start simultane- ously on building the luxury boxes (90 days), installing the seats (140 days), in- stalling the jumbotron (30 days), and installing stadium infrastructure (120 days) which includes: bathrooms, lockers, restaurants, etc. Once the seats are installed then the steel canopy can be constructed (75 days) followed by the installation of the lights (30 days) The retractable roof represents the most significant technical challenge to the project. Building the roof track supports (90 days) can begin after the lower con- crete bowl is constructed. At this time the dimensions of the roof can be finalized and the construction of the roof at a separate site can begin (180 days). After the roof supports are completed then the roof tracks can be installed (90 days). Once the tracks and the roof are completed then the roof can be installed and made op- erational (90 days). Once all activities are completed it will take 20 days to inspect the stadium, For purposes of this case assume the following: 1. The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th. Labor Day (first Monday in September). Thanksgiving Day (4th Thursday in November). December 25 and 26. 2. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off. 3. The construction crew work Monday through Friday. Answer Questions 1-3 and explain. For the case, you are starting on July 1, 2019 ending on May 20, 2022. Use Filipino national holidays with this site as reference: https://www.officialgazette.gov.phationwide-holidays/

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!