Question: 1a.) In table 2 what values shpuld be for X1 and X2? 1b.)What is the project cumulative PV ending period 4? a.) 30 b.) 53
1a.) In table 2 what values shpuld be for X1 and X2?
Activity A B D F G C E G Table 2. Task Duration A 2 B F n D E 3 2 1 2 2 3 96 Completion Finished Finished Finished Finished 30% 67% 0 Budget (PV) 12 15 00 8 6 10 9 5 EV X2 4 3 8 0 4 3 4 AC 13 18 10 8 8 00 7 4 PV X1 3 5 3 3 A 3 6 3 5 4 3 5
1b.)What is the project cumulative PV ending period 4?
a.) 30
b.) 53
c.) 65
d.) 70
1c.) What is project SPI ending period 4?
a.) 0.87
b.) 0.94
c.) 1.05
d.) 1.21