Question: 1A) MRP planned receipts (PR) for item AA are calculated using the Part Period Balancing Algorithm. A PR order for week 1 is scheduled and
1A) MRP planned receipts (PR) for item AA are calculated using the Part Period Balancing Algorithm. A PR order for week 1 is scheduled and will include the week 2 requirements. The week 3 requirements are 95 units. The order cost is $ 32 and the holding cost rate is $ 0.13 /week. What is the holding cost for the 95 units if they are added to the week 1 PR order? 2 decimal places in $
1B) For the above problem, we should add the week 3 requirements to the week 1 PR order?