Question: 1.Calculate the Performance Indices. Cost Performance Index Schedule Performance Index Earned Value Exercise Project Plan: Produce 8 widgets in 8 months. There is no learning

1.Calculate the Performance Indices. Cost

1.Calculate the Performance Indices.

Cost Performance Index

Schedule Performance Index

Earned Value Exercise Project Plan: Produce 8 widgets in 8 months. There is no learning curve effect. Start End Total Cost Total Time 8 months Production Rate Jan 1 Aug 31 1/month $800,000 Current Status at end of April Start Current Date Cost to Date Number Produced Jan 1 April 30 3 $375,000