Question: 1-Construct the project network. 2-Find the critical path and the expected project completion time. 3- What is the probability of completing the project on or

1-Construct the project network. 2-Find the critical path and the expected project completion time. 3- What is the probability of completing the project on or before 37 weeks? 4- What is the time required to complete the project with a probability of 60%

1-Construct the project network. 2-Find the
Consider Table below summarizing the details of a project L A B D Activity predecessor To Tm G CD 3 E A,B 3 8 10 A 1 2 5 F C D 2 5 8 H F 1 2 4 6 15 20 3 6 12 1 E 1 2 4 6 9 K DH 5 10 15 M G 2 4 J E 4 10 15 3 5 10 6 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!