1.Resource leveling or smoothing can have all the following results on a project EXCEPTSingle choice. (1 Point)...
Question:
1.Resource leveling or smoothing can have all the following results on a project EXCEPTSingle choice.
(1 Point)
Lower peak resource demand.
Reduced resource need
A longer project duration
2.All of the following are types of resource constraints EXCEPTSingle choice.
(1 Point)
Material
People
Equipment
Information
3.When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is calledSingle choice.
(1 Point)
Outsourcing
Redistribution of projects
Project allocation
Task sharing
4.In a resource-constrained project, which of the following is most likely to be changed?Single choice.
(1 Point)
The completion date
The budget
Project quality
Resource levels
5.Resources are adequate, but demand varies widely over the life of the project. Delaying noncritical activities to lower peak demand on resources is known as resourceSingle choice.
(1 Point)
Shifting
Manipulating
Smoothing