Question: 1-The Critical Path Method (CPM) of computing the project completion time assumes that Group of answer choices a) the duration of each activity is known

1-The Critical Path Method (CPM) of computing the project completion time assumes that

Group of answer choices

a) the duration of each activity is known with zero error.

b) the error in activity time estimates follows a bell curve.

2-The CPM estimate for a project is 50 days. It follows that

a) exactly one path in the project network has a length of 50 days.

B) at least one path in the project network has a length of 49 days.

c) at least one path in the project network has a length of 50 days.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!