Question: 1)Using the information from the chart above, Please calculate the Availability Rate, to two decimal places 2)Using the information from the chart above, Please calculate

1)Using the information from the chart above, Please calculate the Availability Rate, to two decimal places
2)Using the information from the chart above, Please calculate the Performance Rate, to two decimal places.
3)Using the information from the chart above, Please calculate the Quality Rate, approximately to two decimal places.
700 650 18% 44% 70 650 600 50 530 31% 550 76 500 450 42 412 21 380 400 364 16 350 300 250 200 150 100 50 0 Out of Available Planned Run Time non- production Unsche- Scheduled Break- Change- Available Reduced Stoppages Used duled time run time downs run time throughput time overs run spec batches Effective production time Availability Rate Performance Rate Quality Rate
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts