Question: 1.You are evaluating a project with a cost at time 0 of $1,000 and earnings of $500 per year for 10 years starting in year
1.You are evaluating a project with a cost at time 0 of $1,000 and earnings of $500 per year for 10 years starting in year 7. If the discount rate is 10%, what is the NPV of the project?
a.$1,734.29
b.$734.22
c.$1,048.11
d.$2,072.28