Question: 2 0 2 4 PCM 4 7 0 S GROUP TASK _ PT DUE DATE 1 0 MAY 2 0 2 4 AT 2 3

2024 PCM470S GROUP TASK_PT
DUE DATE 10 MAY 2024 AT 2359
EMAIL TO
matandej@cput.ac.za
Instructions: Attempt all questions and show all calculations. No calculation, no answer. Group size MUST be a minimum of 5 and maximum of 7 members.
Power Engineering is subcontracted to provide technical support for a new hydrogen manufacturing plant in Northwest Province, South Africa. They entered a contract with the following condition.
The subcontract is valued at R10 million. Should the works be completed to the client's satisfaction at a cost lower than its agreed value, then the subcontractor shall be entitled to a cost-saving incentive of 50% of the savings. On the contrary, should the costs be exceeded, the subcontractor shall be held accountable and pay the full extra costs incurred. Calculate how much Power will get or pay (in incentives) under the following conditions.
1.1. The works are finished at a cost of R7 million.
[6 marks]
1.2. The works are completed at a cost of R11 million.
[6 marks]
2.. Indicate how much profit or loss Siyazama Projects (Pty) Ltd will make under the following fixed price contracts.
a) Siyazama was contracted to pave a 20km road at a fixed cost of R18 million. The project costed R11 million.
b) Siyazama charged Bows Investments R5 million to build a small bridge. The project cost was R5 million.
c)3. Siyazama charged R200 million to repair flooddamaged powerlines. The total cost was R250 million.
]=[9 marks
Your organisation is considering whether to hire or buy construction equipment for a cost-constrained social housing project they recently secured. If you buy, the cost is two million rand (R2500,000), and the cost of procurement and integrating in your company is three hundred and fifty thousand rand (R450,000). If you hire, you pay two hundred thousand rand (R300,000 per month for 9 months. The additional overhead costs apportioned to hiring it will be R500,000. Which option will you choose- buy or hire? Show all calculations. [10 marks]
The table below shows a cost-plus incentive contract for a project with a floor of R40 million, a target of R50 million and acoiling of R70 millinn If the client meets
 2024 PCM470S GROUP TASK_PT DUE DATE 10 MAY 2024 AT 2359

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!