Question: ( 2 0 % ) Consider P _ 3 | prmp | Sigma Cj with the additional constraint that the completion of job j
Consider P prmp Sigma Cj with the additional constraint that the completion of job j has to be less than or equal to a given fixed deadline dj Preemptions may occur only at integer times Find the optimal schedule and compute the total completion time.