Question: ( 2 0 % ) Consider P _ 3 | prmp | Sigma Cj with the additional constraint that the completion of job j

(20%) Consider P_3| prmp |\Sigma Cj with the additional constraint that the completion of job j has to be less than or equal to a given fixed deadline d_j. Preemptions may occur only at integer times 1,2,3,... Find the optimal schedule and compute the total completion time.