Question: ( 2 0 ' ) Consider Q 2 | | prmp | C m a x | with the jobs under the Longest Remaining Processing

(20') Consider Q2|| prmp |Cmax| with the jobs under the Longest Remaining Processing Time first (LRPT) schedule.
\table[[jobs,1,2,3,4],[pj,36,24,16,12]]
and machine speeds vl=2 and v2=1.
(a) Find the makespan under LRPT when preemptions can only be made at the time points 0,4,8,12, and so on.(5')
(b) Find the makespan under LRPT when preemptions can only be made at the time points 0,2,4,6,8,10,12, and so on.(5')
(c) Find the makespan under LRPT when preemptions can be made at any time. (5')
(d) Compare the makespans under (a),(b), and (c).(5')
 (20') Consider Q2|| prmp |Cmax| with the jobs under the Longest

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!