Question: ( 2 0 Marks ) A building construction company was awarded a project. The project manager has been very concerned with the amount of time

(20 Marks)
A building construction company was awarded a project. The project manager has been very concerned with the amount of time it took to complete several recent jobs. The data (all in days) for the new contract are listed in the following table:
\table[[Activity,\table[[Immediate],[Predecessor]],Duration],[,,],[A,cdots-cdots,2],[B,cdots-cdots,4],[C,cdots-cdots,2],[D,dots-cdots,5],[E,A, B,2],[F,C, D,3],[G,D,6],[H,C, E,3],[I,F, G, H,5],[J,E, H,9]]
3.1 Construct an AON network for the activities of this contract.
(10 marks)
3.2 Determine the different paths and identify the critical path for the project.
(10 marks)
 (20 Marks) A building construction company was awarded a project. The

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!