Question: [ 2 0 marks ] Given the following info for two periodic processes: table [ [ Process , CPU Time,Cycle Time ( Period )

[20 marks] Given the following info for two periodic processes:
\table[[Process,CPU Time,Cycle Time (Period)],[A,10,20],[B,15,30]]
For 3 instances of A and 2 instances of B, draw a schedule for Earliest-deadline Scheduling using Completion Deadlines.