Question: ( 2 0 points ) : A worker is responsible for loading and unloading the CNC machine producing special bolts. Each cycle, 1 bolt is
points: A worker is responsible for loading and unloading the CNC machine producing
special bolts. Each cycle, bolt is produced, the loadunload elements have total normal time
of seconds, and the machine time is minutes. Every sixth cycle, the operator must do
quality parameter checks on the CNC which takes minutes and seconds normal time
Company uses PFD allowance factor as and the machine allowance factor as
points Determine the standard time for the process and the corresponding standard
daily production quantity for an hour shift.
points Company found a way to internalize the irregular element quality checking
This means, in the th cycle, quality checking on the CNC can be done while the CNC is
working. Determine the standard time for the modified process and the corresponding
standard daily production quantity for an hour shift.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock