[20 points] Environment Recycling, Inc. must clean up a large automobile tire dump under a state environmental cleanup contract. The project activity times are not certain due to various reasons and the following table shows the time estimates for activity times. Activity times are assumed to follow a Beta distribution:
\table[[Activity,\table[[Immedlate],[Predecessor]],\table[[Optimistic Time],[(weeks)]],\table[[Most Probable],[Time (weeks)]],\table[[Pessimistic Time],[(weeks)]]],[A,none,6,8,10],[B,none,8,10,12],[C,A, B,4,6,8],[D,B,4,5,6],[E,C,10,12,14],[F,C,6,7,8],[G,D, E,8,12,16],[H,F, G,6,8,10]]
MGMT 3106: Management Science and Operations Management
a. Calculate the expected time and variance for each activity.
b. Create the activity schedule and calculate ES, EF, LS, and LF times. Activity schedule is a table with ES, EF, LS, LF times for each activity.
c. Calculate the slack for each activity.
d. Determine the estimated project completion time and the standard deviation of the critical path. Show all calculations.
e. Explain why this project has an estimated project completion time and a standard deviation.
 [20 points] Environment Recycling, Inc. must clean up a large automobile

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!