Question: [ 2 0 points ] Environment Recycling, Inc. must clean up a large automobile tire dump under a state environmental cleanup contract. The project activity
points Environment Recycling, Inc. must clean up a large automobile tire dump under a state environmental cleanup contract. The project activity times are not certain due to various reasons and the following table shows the time estimates for activity times. Activity times are assumed to follow a Beta distribution:
tableActivitytableImmedlatePredecessortableOptimistic TimeweekstableMost ProbableTime weekstablePessimistic TimeweeksAnone,Bnone,CA BDBECFCGD EHF G
MGMT : Management Science and Operations Management
a Calculate the expected time and variance for each activity.
b Create the activity schedule and calculate ES EF LS and LF times. Activity schedule is a table with ES EF LS LF times for each activity.
c Calculate the slack for each activity.
d Determine the estimated project completion time and the standard deviation of the critical path. Show all calculations.
e Explain why this project has an estimated project completion time and a standard deviation.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock