Question: ( 2 0 POINTS ) The table below lists the activity times and precedence requirements for the activities required to complete a new equipment installation
POINTS The table below lists the activity times and precedence requirements for the
activities required to complete a new equipment installation project in a factory. Three time
estimates in weeks are given for each activity: optimistic time, most likely time, and pessimistic
time. a Draw the PERT network diagram for the project, labeling all activities and times. b
Perform a forward pass and backward pass through the network to determine the critical path,
the expected duration of the project, and the slack time for each activity. c What is the
probability that the project will be completed one week or more before the expected
completion time?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock