Question: 2 . [ 1 . 5 pts ] Given the following information: Process: A B C D E F Arrival Time: 0 2 4 6

2.[1.5 pts] Given the following information:
Process: A B C D E F
Arrival Time: 0246810
CPU Burst: 364857
Draw a Gantt chart that illustrate the execution of the given processes using FCFS, SJF, and
RR (quantum =2, ignoring context switching overhead). Compute the average waiting time
and average turnaround time for each scheduling algorithm.