Question: 2 . 1 A certain mine intends to start a bord and pillar mining panel and thereafter perform pillar extraction on the same panel. On

2.1 A certain mine intends to start a bord and pillar mining panel and thereafter perform pillar extraction on the same panel. On surface there is a farmers water borehole. Design panel layout to ensure that the water table in the overburden is preserved. (10 marks)
Given: Bord width of 6m and pillar width of 18 m. Depth below surface 140m. Thickness of dolerite sill 20m intersected at 60m. Goaf angle 300, k-ratio 1.5.