Question: 2 1 . Six subsystem designs have been proposed for a critical part of a communications network. Each will be 'burned in * to eliminate

21. Six subsystem designs have been proposed for a critical part
of a communications network. Each will be 'burned in* to
eliminate the Infant mortality problem. Hence, reliability of the
subsystem will have a constant hazard rate. That Is, the failure
density function will be exponential and reliability may be
expressed as
M t)= e -U
where t Is the mission time. Mission time for the subsystem will
be one year, as a thorough annual preventative maintenance
and recalibration procedure Is standard, returning the
subsystem to 'new* condition. The unit will be on call 24 hours
a day, seven days a week. The design data are as follows:
328 Chapters
System
Annual Equivalent
Initial Cost
Annual
Maintenance Cost X
A $ 9000 $17001.1446886 IO"6
B 980014001.098901110"*
C 1020018001.17582410"6
D 1100013001.07000010-5
E 1100015001.081250 IO"4
F 131009000.998000 IO-5
Using cost-effectiveness analysis, plot reliability versus annual
cost Which subsystems can be eliminated from consideration?
How might you decide among the rest? (6.8)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!