Question: 2. [10 marks] The project network is shown in the following figure. Without considering resource constraint, the duration of the project is 10 weeks. Some

2. [10 marks] The project network is shown in the

2. [10 marks] The project network is shown in the following figure. Without considering resource constraint, the duration of the project is 10 weeks. Some activities (2, 3, 5, and 6) need two of the machines, and some activities (1 and 4) need one of the machines. However, only three machines are available. Develop a resource schedule in the loading chart that follows to resolve the resource conflicts. What is the critical chain(s)? What is the duration of the critical chain(s)? 1 3 5 3 2 3 0 1 1 4 4 8 2 1 2 2 1 3 3 4 8 8 6 10 0 1 0 02 0 0 2 3 3 5 8 8 2 10 0 2 0 3 3 3 3 5 6 Legend ESID EF SL RES SL 2 2 2 5 3 8 LS DUR LE ID RES DUR ES LF SLO 1 2 3 4 5 6 7 8 9 10 11 12 13 1 1 1 0 3 2 2 3 0 3 3 2 4 1 8 4 1 5 3 8 5 2 3 6 2 2 Resources scheduled Resources available 3 3 3 3 3 3 3 3 3 3 3 3 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!