Question: 2 . ( 2 0 ) . 3 . THE EXPECTED TIME TO FINISH A PROJECT IS CALCULATED TO BE 1 0 DAYS. THE STANDARD

2.(20).3.THE EXPECTED TIME TO FINISH A PROJECT IS CALCULATED TO BE 10 DAYS. THE STANDARD DEVIATION IS 4 DAYS. WHAT IS THE PROBABILITY THAT THIS PROJECT WILL BE FINISHED IN LESS THAT 5 DAYS AND MORE THAN 5 DAYS? WITHOUT CALCULATION
 2.(20).3.THE EXPECTED TIME TO FINISH A PROJECT IS CALCULATED TO BE

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!