Question: 2 . 2 . Consider the instance of 1 | | Lmax with the following processing times and due dates. jobs 1 2 3 4
Consider the instance of Lmax with the following processing times and
due dates.
jobs
pj
dj
a Find the optimal sequence and compute the value of the objective.
b Give an argument for positioning jobs with earlier due dates more towards
the beginning of the sequence and jobs with later due dates more
towards the end of the sequence.
c Give an argument for positioning jobs with smaller processing time
more towards the beginning of the sequence and jobs with larger processing
time more towards the end of the sequence.
d Determine which one of the following four rules is the most suitable
generic rule for the problem:
i sequence the jobs in increasing order of dj pj ;
ii sequence the jobs in increasing order of djpj ;
iii sequence the jobs in increasing order of dj ;
iv sequence the jobs in increasing order of pj
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock