Question: 2 . 2 . Consider the instance of 1 | | Lmax with the following processing times and due dates. jobs 1 2 3 4

2.2. Consider the instance of 1|| Lmax with the following processing times and
due dates.
jobs 1234
pj 5436
dj 351112
(a) Find the optimal sequence and compute the value of the objective.
(b) Give an argument for positioning jobs with earlier due dates more towards
the beginning of the sequence and jobs with later due dates more
towards the end of the sequence.
(c) Give an argument for positioning jobs with smaller processing time
more towards the beginning of the sequence and jobs with larger processing
time more towards the end of the sequence.
(d) Determine which one of the following four rules is the most suitable
generic rule for the problem:
(i) sequence the jobs in increasing order of dj + pj ;
(ii) sequence the jobs in increasing order of djpj ;
(iii) sequence the jobs in increasing order of dj ;
(iv) sequence the jobs in increasing order of pj .

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!