Question: 2 3 4 QUESTION 1 During planning, the team has identified the items in the following table as work to be done on the project.

2 3 4

QUESTION 1

During planning, the team has identified the items in the following table as work to be done on the project.

Draw a network diagram to graphically depict this flow.

All relationships are F-S relationships and durations are in days.

TASK

DURATION

SUCCESSOR

A 1 D
B 2 E
C 4 F
D 2 G
E 3 I
F 4 H
G 6 K
H 1 J
I 5 J
J 2 FINISH
K 1 FINISH

Perform a financial analysis for a project. Assume that the projected costs and benefits for this project are spread over four years as follows:

Estimated costs are $300,000 in Year 1 and$ 65,000 each year in Years 2, 3, and 4.

Estimated benefits are $0 in Year 1 and$120,000each year in Years 2, 3, and 4.

Use a10percent discount rate, and round the discount factors to two decimal places.

What is the Net Present Value (NPV)?

Show your work.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!