Question: ( 2 5 points ) Let's now consider a biological treatment of the Sucrase. A pilot - scale treatment system is built to test for
points Let's now consider a biological treatment of the Sucrase. A pilotscale treatment system is built to test for BOD removal efficiency. The sywem is tested with a concentration of of Sucrose. Samples from the influent and effluent of the treatment system are collected and analyzed for BODs. All BOD lests are conducted with a total volume of mL
The samples are diluted with seeded difution water that has a small amount of BOD ilself. To find the BODs of the dilution witer, an experiment containing only the dilution water was performed. The initial DO of the dilution wioner is might. If the final DO of the dilution water is after the day BOD test, what is the BODs of the dilution water?
ii When testing the strength of the wastewarer, mL of the waste solution is used. The initial DO of the mixture is If the final DO of the mixture after days is what is the of the wastewater?
If the pifor treatment system has a substrate removal efficiency of and treats a flow of how much in kg would be required for hours of operation?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock