Question: 2 5 points REMINDER: Quantities are in regular brackets --> () Lead time are in square brackets --> [] End (1) (3) A (2)[1] B

2 5 points REMINDER: Quantities are in regular

2 5 points REMINDER: Quantities are in regular brackets --> () Lead time are in square brackets --> [] End (1) (3) A (2)[1] B (3) (4) C (2)[1] D (4) [3] E (3) [2] F (4) [3] G (2) [2] H (3) [1] F(2) [3] G (3) [2] Item End A B D E On Hand 54 74 82 65 561 390 1346 2173 489 [Lead Time] Direct Components 3 A2, B3, C2 1 D4, E3 4 F4, G2 1 H3 2 2 3 2. F G H N 1 F2, G3 How many of the "A" Component are required to complete 1 "End" item? Type your