Question: ( 2 5 pts . ) a . With a learning rate of 7 5 % in a bicycle manufacturing plant, it took 1 2

(25 pts.) a. With a learning rate of 75% in a bicycle manufacturing plant, it took 124 hours to produce
the first 20 bicycles. Predict how long it will take to make the following 60 bicycles.
b. Explain briefly how your answer to (a) impacts the EPL policy.