Question: [ 2 5 pts . ] Four projects are available for investment. The projects require the cash flows and yield the net present values (

[25 pts.] Four projects are available for investment. The projects require the cash flows and yield the net present values (NPV)(in millions) shown in the following table.
\table[[Project id.,\table[[Cash outflow at time 0],[(million Lira)]],\table[[NPV],[(million Lira)]]],[1,8,12],[2,8,11],[3,6,8],[4,5,6]]
If 20 million Lira is available for investment at time 0, find the investment plan that maximizes NPV. All investments are required to be 0 or 1(fractional investment values are not permitted).
a. Formulate the mathematical model. (Write the decision variables, objective function and the constraints.)[10 pts.]
b. Find the optimal solution by using Branch and Bound method (Draw the branch and bound tree clearly, write also lower bounds(LB))(Left branches xi=0, right branches xi=1)
pts.].
 [25 pts.] Four projects are available for investment. The projects require

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!