Question: 2 7 8 Part 3 Planning Projects Exercises Label the box below to create a two - pass schedule legend. If the learning rate is
Part Planning Projects
Exercises
Label the box below to create a twopass schedule legend.
If the learning rate is percent and the first time the activity was performed took min utes, the second time performing the activity should take minutes, and the fourth time should take minutes.
In the example below, label which activities are predecessors and which activities are successors.
Create a logical network using the activities listed below.
Planting a Flower Bed
Purchase flowers, potting soil, and tools.
Water flowers.
Prepare soil by weeding and adding fertilizer.
Plant flowers.
Dig hole.
Calculate early start, early finish, late start, late finish, and float for each of the activities in the network below. The duration of each activity is given.
Identify the critical path for the network in Exercise How long should the project take?
Display the schedule from Exercise on a Gantt chart showing critical activities, noncritical activities, and float.
Given the information below, create the project schedule network. Then, using the twopass method, calculate and show the early and late starts and float for each activity and the critical path. Show the schedule on a Gantt chart showing critical and noncritical activities and float.
tableACTTVITYDAYS,tableIMMEDIATEPREDECESSORABACADAEBFB CGD E F
Given the information below, create the project schedule network. Then, using the enumeration method, calculate and show all of the paths through the network. Show how long each path will take. Identify the critical path. Show the schedule on a Gantt chart showing critical and noncritical activities and float.
tableACTIVTTYDAYS,tableIMMEDIATEPREDECESORABB
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock