Question: 2 . A construction company is considering submitting a bid on a contract that is worth $ 9 0 0 , 0 0 0 .

2. A construction company is considering submitting a bid on a contract that is worth $900,000. The research and planning needed to write up the bid will cost $40,000. If they are awarded the contract, they will incur an additional $600,000 in expenses to perform the work specified in the contract. Would you advise the company to spend the $40,000 if the bid has only a 20% chance of being accepted? Use the expected profit (loss) to determine why or why not.