Question: 2. A project has been subdivided into five activities. Their immediate predecessors and the estimated activity durations (optimistic, most likely, and pessimistic) are shown in

2. A project has been subdivided into five activities. Their immediate predecessors and the estimated activity durations (optimistic, most likely, and pessimistic) are shown in Table 1

Table 1 Details of the network

Activity Immediate Predecessor Estimate duration (in days)

A - 1, 2, 3

B - 1, 3, 5

C A, B 3, 4, 5

D A, C 2, 2, 2

E C, D 1, 2, 21

(a) Draw the project network. Based on the mean activity durations, calculate all earliest and latest starting and finishing times, and the total floats of all activities. What is the critical path? What is its duration?

(b) Calculate the variance and standard deviation on the critical path.

(c) Calculate the probability that the project will be finished between 11 and 15 days.

(d) What is the probability that the project will be finished within 14 days? What is the probability that the project will be finished in exactly 14 days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!