Question: 2 ) A project has the following activities along with the associated durations in days: Activity Duration in Days Immediate Predecessor A 5 - B
A project has the following activities along with the associated durations in days:
Activity Duration in Days Immediate Predecessor
A
B A
C A
D B
E B
F D E
G C E
H G F
I H
Find out the critical path and the slack times for each activity.