Question: 2 ) A project has the following activities along with the associated durations in days: Activity Duration in Days Immediate Predecessor A 5 - B

2) A project has the following activities along with the associated durations in days:
Activity Duration in Days Immediate Predecessor
A 5-
B 18 A
C 13 A
D 3 B
E 10 B
F 4 D, E
G 11 C, E
H 9 G, F
I 2 H
Find out the critical path and the slack times for each activity.