Question: 2. A proposed project is expected to decrease accounts receivable by $10,000, decrease inventory by $4,000, and increase accounts payable by $6,000. What is the

 2. A proposed project is expected to decrease accounts receivable by
$10,000, decrease inventory by $4,000, and increase accounts payable by $6,000. What

2. A proposed project is expected to decrease accounts receivable by $10,000, decrease inventory by $4,000, and increase accounts payable by $6,000. What is the amount of the initial cash ow for this project? a. -$12.000 b. $0 c. $8.000 d. $20,000