Question: 2. A simple assembly line has tasks A(2), B(5), C(1), and D(2) that need to be done in this order to produce a unit of

2. A simple assembly line has tasks A(2), B(5), C(1), and D(2) that need to be done in this order to produce a unit of product. The numbers in parentheses are task times in minutes. Every unit goes through all 4 steps in the same order.

The capacity of this line in an 10-hour day is:

a. 96

b. 72

c.100

d. 120