Question: 2. A small software development project has 9 major activities. The times are estimated and provided in the network below. Using the method of ES,
2. A small software development project has 9 major activities. The times are estimated and provided in the network below.
- Using the method of ES, EF, LS, and LF, determine the project completion time?
- Find the critical path(s).
- State the non-critical activities.
- Explain what it means if an activity has a slack of zero (give an example).
- Explain what it means if an activity has a slack of non-zero (give an example)