Question: 2) A software company is developing a new app. Each phase must be completed before beginning a new phase as the deliverables from each phase
2) A software company is developing a new app. Each phase must be completed before beginning a new phase as the deliverables from each phase are prerequisites for subsequent phases. What type of life cycle is this?
Group of answer choices
Agile Life Cycle
Iterative Life Cycle
Predictive Life Cycle (Waterfall model)
Incremental Life Cycle