Question: ( 2 ) A Temporary Bench Mark ( TBM ) B is needed to be set up on a tower. There is a Bench Mark

(2) A Temporary Bench Mark (TBM) B is needed to be set up on a tower. There is a Bench Mark A nearby with a known elevation of 19.475mAOD, as shown in Figure Q1; therefore, a level is set up in between to set the TBM. If the elevation of TBM needs to be set as 20.500 mAOD, and the reading from the levelling staff held at A is 1.753m, what will be the reading expected from the levelling staff held on B?