Question: 2) Activity A and B immediate predecessor to activity C and activity B is 6 days long. Activity A has ES =10 and LS=10 activity
2) Activity A and B immediate predecessor to activity C and activity B is 6 days long. Activity A has ES =10 and LS=10 activity B has ES=9 and LS=12. And ES of activity C=21 what is the day long of activity A?