Question: 2 - Assume that we have a simple project, shown below. A ) Without any calculation, what is the critical path? Briefly explain why. B

2- Assume that we have a simple project, shown below.
A) Without any calculation, what is the critical path? Briefly explain why.
B) How long does it take to finish this project?
C) How many days can you delay activity C without affecting the project
finish date?
D) What is the latest time you can start activity C without affecting the
project finish date?