Question: 2. Conduct PERT analysis for the data by; a) Constructing AOA diagram b) Identifying due time of the critical path c) Compute for te, Path

2. Conduct PERT analysis for the data by; a)

2. Conduct PERT analysis for the data by; a) Constructing AOA diagram b) Identifying due time of the critical path c) Compute for te, Path total, v2, v2 path, v path of the critical d) Compute for z value, the Pz (Normal standard distribution) and plot in a graph ACTIVITY IMMEDIATE PREDECESSORS to tm tp A,B AC A B C D E F G H B,C TIME ESTIMATES (days) 2 3 6 5 4 8 7 5 4 10 5 4 3 2 DE D,F E,F G H GI HI J K L,M 1 2 5 3 2 5 3 4 2 8 3 2 2 1 3 3 7 5 4 7 6 6 5 9 5 3 3 2 5 4 8 7 6 10 8 7 6 12 7 5 5 4 J K L M 0