Question: 2. Consider the following table and assumptions given below for calculation. Information Domain Count External Inputs External Outputs External Inquiries Internal Logical Files External Interface
2. Consider the following table and assumptions given below for calculation. Information Domain Count External Inputs External Outputs External Inquiries Internal Logical Files External Interface Files 11 5 Simple Average Difficult FP Count 12 4 7 13 TOTAL Past projects show burdened labour rate 6000BD/PM Average productivity is 8FP/PM Assume difficult complexity with the total adjustment value to be 48. Find FPE, Project Effort and the Project cost.(4 Marks of efforts +1 mark for estimation of cost) 2 mark for FPE 1 mark for estimation