Question: 2 ) Consider the two - step process. Step A has a processing time of 2 minutes per unit and a setup time of 1

2) Consider the two-step process. Step A has a processing time of 2 minutes per unit and a
setup time of 10 minutes. Step B has a processing time of 4 minutes per unit, but no setup
time is required. There is a buffer between steps A and B if there is a minor delay in operation.
30 points
a) Draw the flow chart for this problem.
b) Suppose units are produced in batches of 15. Which step is a bottleneck, and what is the
capacity of the process (in units per minute)?
c) What is the batch size that maximizes the flow rate of this process with minimal inventory?
Assume there is significant demand.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!