Question: #2) Data for a project are given below: NOTE : Include 3 decimals in your calculations. Activity Immediate Predecessor(s) Time Estimates (weeks) Optimistic Most Likely
#2) Data for a project are given below:
NOTE: Include 3 decimals in your calculations.
| Activity | Immediate Predecessor(s) | Time Estimates (weeks) |
|
| ||
| Optimistic | Most Likely | Pessimistic | Expected Time | Variance
| ||
| A | - | 5 | 7 | 8 | 6.833 | 0.250 |
| B | - | 6 | 8 | 12 | 8.333 | 1.000 |
| C | - | 3 | 4 | 5 | 4.000 | 0.111 |
| D | A | 11 | 17 | 25 | 17.333 | 5.444 |
| E | B | 8 | 10 | 12 | 10.000 | 0.444 |
| F | C,E | 3 | 4 | 5 | 4.000 | 0.111 |
| G | D | 4 | 8 | 9 | 7.500 | 0.694 |
| H | F | 5 | 7 | 9 | 7.000 | 0.444 |
| I | G,H | 8 | 11 | 17 | 11.500 | 2.250 |
- Perform the necessary calculations and determine the expected completion time for the project. (3 points)
- What is the joint probability of completing the entire project in 42 weeks or less. Perform the necessary calculations and complete entries in the table below. (7 points)
| Path | Probability (length 42 weeks) | |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
|
|
|
|
|
|
Joint probability of completing the project in less than 42 weeks or less = _________