Question: 2 . Define the Critical Path and calculate the Project Completion Time and the probability that the project will take more 4 9 time periods

2. Define the Critical Path and calculate the Project Completion Time
and the probability that the project will take more
49 time periods to complete. Enter Answers in yellow cells.
Activity Expected Time Standard Deviation of Time Estimate Immmediate Predecsssor Column1
A 72-4
B 31 A 1
C 93 A 9
D 41 B, C 1
E 51 B, C 1
F 82 E 4
G 81 D,F 1
H 62 G 4