Question: 2 Demand for a certain subassembly in a toy manufacturing facility at the North Pole is 96 items per eight-hour shift of elves. The following

 2 Demand for a certain subassembly in a toy manufacturing facility

2 Demand for a certain subassembly in a toy manufacturing facility at the North Pole is 96 items per eight-hour shift of elves. The following six tasks are required to produce one subassembly: What is the required cycle time? Theoretically, how many stations will be required? Balance the line. What is the line's efficiency