Question: 2. Determine Project Y's payback period. 4. Determine Project Y's net present value using 9% as the discount rate. (Do not round intermediate calculations. Round





2. Determine Project Y's payback period. 4. Determine Project Y's net present value using 9% as the discount rate. (Do not round intermediate calculations. Round your present value factor to 4 decimals and final answers to the nearest whole dollar.) 3. Compute Project Y's accounting rate of return. Required: 1. Compute Project Y's annual net cash flows. Required information [The following information applies to the questions displayed below.] Project Y requires a $333,000 investment for new machinery with a six-year life and no salvage value. The project yields the following annual results. Cash flows occur evenly within each year. (PV of $1,FV of $1, PVA of $1 , and FVA of \$1) (Use appropriate factor(s) from the tables provided.)