Question: 2) Five jobs arrive nearly simultaneously for processing and their estimated CPU cycles are, respectively: Job A = 2 ms, Job B = 12 ms,

2) Five jobs arrive nearly simultaneously for processing and their estimated CPU cycles are, respectively: Job A = 2 ms, Job B = 12 ms, Job C = 15 ms, Job D = 7 ms, and Job E = 3 ms.

a. Using FCFS, in what order would they be processed? What is the total time required to process all five jobs? What is the average turnaround time for each of these five jobs?

b. Using SJF, and assuming that all jobs are present when the algorithm begins, in what order would they be processed? What is the total time required to process all five jobs? What is the average turnaround time for all five jobs?

c. Using SJF, and assuming that all jobs are present when the algorithm begins, what is the average turnaround time for all five jobs using these speeds: Job A = 12 ms, Job B = 2 ms, Job C = 15 ms, Job D = 7 ms, and Job E = 3 ms.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!