Question: 2. For the following schedule draw the node network, perform the CPM calculations, mark the critical path, and complete the table below. Then, impose a

 2. For the following schedule draw the node network, perform the

2. For the following schedule draw the node network, perform the CPM calculations, mark the critical path, and complete the table below. Then, impose a constraint on F to start on day 31 and recalculate the CPM and the values in the table. What happen to the critical path