Question: 2. For the project network shown, do the followings: (25 points) a) Calculate activities' Total Floats (TF), b) Identify the critical path and determine project

2. For the project network shown, do the
2. For the project network shown, do the followings: (25 points) a) Calculate activities' Total Floats (TF), b) Identify the critical path and determine project completion time or duration, c) What is the effect of delaying activity H by 6 days on project duration? Note: Assume activity durations are in days I Dummy G 1 1 Bood I K k Sna F (8)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!